Microsoft 74-343 Exam Certification helps you to pass your exam in first attempt. You can easily prepare your 74-343 exam with the help of dumps. Dumps4download.in is top rated website that is well know in IT students and all IT professionals. Dumps4download providing fully reliable 74-343 study questions that are fully verified by IT professionals. 

You can get 74-343 Dumps in PDF and 74-343 questions in exam engine format. We are fully sure that you will enjoy our Microsoft 74-343 study questions. you will definitely pass your exam with Microsoft practice questions. 70-343 exam sample questions are easy to remember you can also download these Microsoft practice questions and get help in offline mode. Dumps4download is totally user friendly website you can get exam help and easily share your reviews about sample questions.


Get Latest Dumps Question Answer For Microsoft 74-343 Exam - Dumps4download.in

Skills Measured:

This exam measures your ability to accomplish the technical tasks listed below. The percentages indicate the relative weight of each major topic area in the exam. The higher the percentage, the more questions you are likely to see on that content area in the exam. View video tutorials about the variety of question types on Microsoft exams.



Exam Code  :  70-343


Published  :  05 April 2013


Languages  :  English, Portuguese (Brazil), Spanish


Audiences  :  Partners


Technology  :  Microsoft Project


Credit towards certification  :  MCP


Registration  :  $80.00 USD*



Exact Microsoft 74-343 Exam Dumps Questions Sample Question 6

While creating a schedule with Project Professional 2013, you notice that there is a three day duration on the Database Design task. After working for only two days, the resource performing the task reports two days of work and notifies you that the task is finished. You need to update the schedule with this information. What should you do?

A. Reschedule uncompleted work for the project schedule.
B. Add two days of actual duration and change the remaining duration for the task to zero.
C. Update the task to show 100% completion on the ribbon bar.
D. Enter a status date for the task.

Read more

Free 74-343 Dumps Question Number 5

You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks. You create two manually scheduled tasks and link them in a Finish to Start relationship. The project team member asks you to increase the duration of the predecessor task. You notice that the successor task start date is now before the finish date of the predecessor task. You want the successor task to start after the predecessor finishes. What should you do?

A. Select both tasks and click Unlink.
B. Select the successor task and click Mark on Track.
C. Select the predecessor task and click Respect Links.
D. Select the successor task and click Respect Links.

Read more

Free 74-343 Dumps Question Number 4

You are a project manager who uses Project Standard 2013, and your task list includes a flag field that indicates, with Yes or No, if a non-summary task represents a physical deliverable. Your project involves several tasks marked as deliverables, and management requires you to track how many deliverables are completed. The deliverable is considered completed when the Percent complete field is 100%. You need to create a formula to calculate the total number of deliverables that are completed. Which two steps should you perform? (Each correct answer presents part of the solution. Choose two.)

A. Use the following formula: IIf([Physical Deliverable]=Yes And [% Complete]=100,1,0).
B. Set Calculation for tasks and summary groups to Sum.
C. Use the following formula: IIf([Physical De
D. Set Calculation for tasks and summary groups to Count All. liverable]=Yes And [% Complete]=100,0,1).

Read more

Free 74-343 Dumps Question Number 3

You manage a project schedule by using Project Professional 2013. You are concerned about project costs. After viewing the Cost Variance column, you realize that the project has a cost variance of 55,000.00. You need to view graphically which tasks and resources are causing the $5,000.00 cost variance. What should you do?

A. View the Resource Graph's Cumulative Cost view.
B. View the Task Cost Overview report.
C. View the Over Budget Tasks report.
D. View the Cost Overrun report

Read more

Free 74-343 Dumps Question Number 2

You are a project manager who uses Project Professional 2013. You need to change the default for all new projects so that tasks will be created in Auto Scheduled mode. What should you do?

A. For each new project, use the Status Bar to set new tasks to be auto scheduled.
B. For each new project, use the Auto Schedule button on the Tasks tab.
C. Open the Global.mpt and use the Auto Schedule button on the Tasks tab.
D. Set the Default task type to Auto Scheduled for All New Projects in the Schedule Options.
E. Set the New tasks created option to Auto Scheduled and set the Schedule Options to All New Projects

Read more

Free 74-343 Dumps Question Numbe 1

You manage a project for an organization that relies heavily on schedule baselines in Project Standard 2013.A change is approved for an in-progress project which you manage. You enter the new tasks necessary to include the changes to the project schedule.You need to update the baseline in the most efficient manner.What should you do?


A. Update the current baseline to the baseline1 fields.
B. Copy the current schedule to the baseline fields.
C. Select a range of tasks and update the schedule to the baseline1 fields for the selected tasks.
D. Select a range of tasks and update the baseline for the selected tasks.

Read more